Eskom has announced that it has returned Kusile power station’s unit 1 to service, and it is on load. Eskom stated by saying: “The unit is returned to service a month and a half ahead of the original schedule and brings an additional 800MW into the grid. This is after Kusile Unit 3 was returned

Kusile-power-station-coming-back-online-after-catastrophic-collapse

Kusile-power-station-coming-back-online-after-catastrophic-collapse

Share
Picture: News24
Advertisement

Eskom has announced that it has returned Kusile power station’s unit 1 to service, and it is on load.

Eskom stated by saying: “The unit is returned to service a month and a half ahead of the original schedule and brings an additional 800MW into the grid. This is after Kusile Unit 3 was returned to service on 30 September 2023 and consistently delivering 800MW.”

The state-owned power utility revealed that the return of both units signifies that it is on the right path to reducing and ultimately ending load-shedding. Kusile units 1, 2, and 3 were taken offline due to the collapse of a part of the flue duct in late October 2022.

It is said that the faulty emission control systems and human errors led to a cement-like deposit forming in the flue-gas duct of the Kusile power station, causing a part of the chimney-like structure to collapse on the 23rd of October 2022.

Eskom publicly confirmed the failure at the power station near Emalahleni in Mpumalanga on the 2nd of November 2022 — 10 days after it occurred.

Reporting for Business Tech Africa on the funding, tools and strategy shaping the continent's founders and SMEs.

Was this useful?0 reactions
Oil Rig
Read nextenergy

BW Energy Suspends Gabon Operations After Offshore Rig Sinks

BW Energy has suspended production at its MaBoMo facility offshore Gabon after the Prospector 5 drilling rig sank during preparations for a planned drilling campaign on 24 October 2026.

Roy Mulenga · readContinue reading