Tullow Oil Agrees to $196.5m Ghana Tax Settlement With Payments Extended to 2032
Tullow Oil has agreed to pay Ghana $196.5 million to resolve two tax disputes, with additional payments tied to oil prices and future gas revenue from the Jubilee field.

Tullow Offshore Platform
Tullow Oil has agreed to pay Ghana $196.5 million in cash to settle two long-running tax disputes involving assessments of $387 million before penalties, with the government also set to receive revenue from future gas production at the offshore Jubilee field.
Announced on November 23, 2026, the agreement follows years of disagreements over the taxation of insurance compensation and the deductibility of interest on loans. The settlement requires an initial payment of $112 million, with two further instalments scheduled for 2027 and 2028.
The disputes involved tax assessments of $196.5 million and $190.5 million, each carrying a 100% penalty.
The first concerned insurance proceeds Tullow received following business interruptions between 2016 and 2019. The second involved whether interest payments on loans could be deducted for tax purposes.
On September 29, an arbitral tribunal operating under International Chamber of Commerce (ICC) rules ruled in Ghana's favour in the insurance proceeds dispute, rejecting Tullow's claims and upholding the government's right to tax the compensation.
The loan interest dispute was still before the ICC when the settlement was announced. The agreement provides a way to resolve the matter without waiting for the arbitration to conclude.
Ghana to Receive Payments Over Several Years
Under the settlement, Tullow will pay Ghana $112 million upfront, followed by $40 million in 2027 and $44.5 million in 2028.
The company can defer the two later payments if the annual average oil price falls below $90 per barrel. However, both instalments must be settled by 2032.
Beyond the cash payments, Ghana will receive revenue from approximately 100 billion cubic feet of gas produced at the offshore Jubilee field. Transfers are scheduled to begin in 2029, although Tullow can postpone them until 2032.
The company has not disclosed the estimated monetary value of the gas revenue included in the arrangement, making the total value of the settlement higher than the $196.5 million cash component.
Settlement Tied to Jubilee and TEN Investments
The Ghanaian government has approved the agreement, but it still requires parliamentary approval before it can take effect.
Finance Minister Cassiel Ato Forson said the settlement would secure revenue owed to the country. Tullow, meanwhile, said resolving the disputes would support its refinancing plans and continued investment in its Jubilee and Tweneboa, Enyenra and Ntomme (TEN) developments.
The agreement gives Ghana an immediate $112 million payment while spreading the remaining cash obligations and gas revenue transfers over several years.