Funding & Finance

OASIS 1: Mookodi BESS  Project reaches Commercial Close

In less than a year after being awarded under the DMRE’s Energy Storage Independent Power Producers Procurement Programme (ESIPPPP), the Oasis 1: Mookodi battery energy storage systems (BESS) project reached commercial close on 16 October 2024, with the signing of project documents in Cape Town, in the presence of the Minister of Electricity and Energy

OASIS 1: Mookodi BESS  Project reaches Commercial Close

OASIS 1: Mookodi BESS  Project reaches Commercial Close

Share
L-R: Jacob Mbele – DG of the DMRE, Laurent CLEMENT – VP EDF AFRICA, Dr Kgosienthsho Ramokgopa – Minister of Electricity & Energy, Alberto Gambacorta – VP Business Development at Skatek, Segomoco Scheppers Interim Chief Executive Officer – National Transmission Company South Africa, Tshifhiwa Magoro- Head at IPP Office
Advertisement

In less than a year after being awarded under the DMRE’s Energy Storage Independent Power Producers Procurement Programme (ESIPPPP), the Oasis 1: Mookodi battery energy storage systems (BESS) project reached commercial close on 16 October 2024, with the signing of project documents in Cape Town, in the presence of the Minister of Electricity and Energy Dr Ramokgopa, the NTCSA, the DMRE, the Project Sponsors, including EDF, Pele, Gibb-Crede, Mulilo and the project lenders.

The Financial Close is scheduled to follow in November 2024. The project is expected to be constructed within 24 months.

The South African Department of Mineral Resources and Energy (DMRE) awarded preferred bidder status to five projects of Round 1 of the Energy Storage Independent Power Producer Programme (ESIPPP1) in November of 2023.

The Oasis consortium, which was awarded three of the five projects, is led by EDF in collaboration with local entity EDF Renewables (EDFR), and includes co-sponsor Mulilo, and equity partners Pele Energy Group and Gibb-Crede. Each project includes a 5% ownership interest for local communities through a Community Trust.

The Oasis 1 portfolio comprises of three separate projects: Oasis Mookodi (77 MW capacity with 308 MWh storage), Oasis Aggeneis (77 MW capacity with 308 MWh storage), and Oasis Nieuwehoop (103 MW capacity with 412 MWh storage), totalling 257 MW of capacity and 1028 MWh of storage. All projects are all located in the Northern Cape Supply Area.

The Oasis 1 BESS projects form part of the first of three procurement rounds for the Battery Energy Storage Independent Power Producer Programme in South Africa

Advertisement

The batteries will be dispatched through the national grid and provide three applications:

1. Grid constraint relief:

Helping to relieve grid constraints, and increase the uptake of renewable energy, by absorbing power that cannot be evacuated and releasing it during peak times.

2. Energy Arbitrage:

Helping to shift cheap energy produced during low-demand periods to peak hours, avoiding/minimizing the use of diesel generators.

3. Ancillary services:

Helping to stabilize the grid for short periods of time (seconds – minutes, sometimes hours) by providing/absorbing power.

Reporting for Business Tech Africa on the funding, tools and strategy shaping the continent's founders and SMEs.

Was this useful?0 reactions
FCSL launches app that lets Nigerians practise stock trading before risking real money
Read nextFunding & Finance

FCSL launches app that lets Nigerians practise stock trading before risking real money

Getting someone interested in investing is easy. Getting them to put their money into the market is harder. FCSL Asset Management wants to tackle that problem with InvestEd+, a new mobile app that lets Nigerians learn about the stock market and practise trading before using real money. The app uses live Nigerian Exchange (NGX) market

Vutomi Manzini · 3 min readContinue reading