ExxonMobil Approves $4 Billion Angola Oilfield Redevelopment to Extend Block 15 Production
ExxonMobil and its partners have approved a $4 billion redevelopment of Angola's Kizomba A and B fields, alongside the Likembe development, as they seek to recover remaining offshore oil resources and extend Block 15 production through 2037.

Offshore Kizomba
ExxonMobil and its partners have approved an estimated US$4 billion investment to redevelop Angola's Kizomba A and B oil fields in offshore Block 15, as the company moves to recover additional resources from assets that have been producing for more than two decades.
The partners reached a final investment decision (FID) on 19 November 2026, completing another major approval under the Block 15 life-extension programme. The decision follows approval of the Kizomba C redevelopment in 2025, according to Angola's National Oil, Gas and Biofuels Agency (ANPG).
The investment will focus on extending production from existing facilities and accessing remaining oil resources across the Kizomba Hub. It also includes the development of the Likembe field, which will be connected to existing offshore infrastructure rather than requiring a new production platform.
According to ExxonMobil Angola Managing Director Brian Unietis, the investment forms part of the company's wider effort to maximise recovery from Block 15. An extension of the block's production-sharing agreement through 2037 gives the partners a longer operating window to develop the remaining resources.
ExxonMobil targets remaining oil in mature fields
ExxonMobil has held interests in Block 15 since 1994, with production beginning at the Xikomba field in 2003. Kizomba A followed in 2004, Kizomba B in 2005 and Kizomba C in 2008.
Production across the block peaked at more than 600,000 barrels per day, but output has declined as the offshore fields have matured. Mordor Intelligence estimates that ExxonMobil's Kizomba assets are now about 85% depleted, making improved recovery from existing reservoirs increasingly important to the block's future production.
The redevelopment programme will use existing wells, subsea infrastructure and offshore facilities to access resources that remain in the fields.
Likembe is another part of that strategy. The Redevelopment 2.0 Likembe Project will connect the subsea field to existing Block 15 facilities, avoiding the cost of constructing a separate production platform.
In April 2026, Subsea Integration Alliance, a partnership between Subsea7 and SLB OneSubsea, secured an engineering, procurement, construction and installation (EPCI) contract valued between US$150 million and US$300 million for the Likembe development.
The approach allows the partners to develop additional offshore resources while making use of infrastructure already operating in the block.
Angola works to keep oil production near 1 million barrels a day
The investment comes as Angola faces declining output from several mature offshore fields. The country, sub-Saharan Africa's second-largest crude producer after Nigeria, has been working to attract fresh investment and maintain national production at around 1 million barrels per day.
Regulatory reforms, new licensing initiatives and extensions to existing production agreements form part of the government's efforts to sustain the petroleum industry.
Recent exploration activity in Block 15 has also identified additional resources. The Tchihumba West-01ST1 exploration well, drilled by the Valaris DS-9 drillship approximately 350 kilometres northwest of Luanda, encountered 65.4 metres of hydrocarbon-bearing sandstone with good petrophysical properties. The well was drilled in water approximately 1,400 metres deep.
The discovery represents the 21st recorded in Block 15 and the second announced in 2026, following the Vicango Este-01 discovery in September.
Further appraisal and development work will be required before the Tchihumba West discovery can contribute to commercial production. Unlike that exploration programme, the Kizomba and Likembe investments focus on developing identified resources and connecting them to infrastructure already in place.
The Block 15 production-sharing agreement now runs through 2037, while the latest investment approval covers the redevelopment of Kizomba A and B and the development of Likembe.